Freedom Toaster Schedule

From WLCS

Schedule // October (2008) -> April (2009)

    • October --> Mid January: Protocol
    • January --> April: Delivery
  • October & November
    • Start of Project
    • Collect Computer Parts: Motherboards, CPU, Disk,
    • Decide on OS (Ubuntu), Kiosk (Freedom Toaster), Software
    • Sketch Initial Design on Paper & Physical Dimensions of The Kiosk
    • Decide on Physical Location of Kiosk (W-L Cyber Cafe)
  • December
    • Work on The Protocol
    • Test Touchscreen
  • January
    • Test Protocol
    • Decide on Contents
  • February
    • Aesthetic Design
    • Develop Part List
    • Final Design - CAD
    • Order Parts
  • March
    • Assembly
  • April
    • Delivery The Kiosk To Physical Location