Difference between revisions of "Freedom Toaster Schedule"
From WLCS
(New page: test) |
|||
| Line 1: | Line 1: | ||
| − | + | ''' Schedule // October (2008) -> April (2009)''' | |
| + | ** October --> Mid January: Protocol | ||
| + | ** January --> April: Delivery | ||
| + | * October & November | ||
| + | ** Start of Project | ||
| + | ** Collect Computer Parts: Motherboards, CPU, Disk, | ||
| + | ** Decide on OS (Ubuntu), Kiosk (Freedom Toaster), Software | ||
| + | ** Sketch Initial Design on Paper & Physical Dimensions of The Kiosk | ||
| + | ** Decide on Physical Location of Kiosk (W-L Cyber Cafe) | ||
| + | * December | ||
| + | ** Work on The Protocol | ||
| + | ** Test Touchscreen | ||
| + | * January | ||
| + | ** Test Protocol | ||
| + | ** Decide on Contents | ||
| + | * February | ||
| + | ** Aesthetic Design | ||
| + | ** Develop Part List | ||
| + | ** Final Design - CAD | ||
| + | ** Order Parts | ||
| + | * March | ||
| + | ** Assembly | ||
| + | * April | ||
| + | ** Delivery The Kiosk To Physical Location | ||
Latest revision as of 16:11, 11 December 2008
Schedule // October (2008) -> April (2009)
- October --> Mid January: Protocol
- January --> April: Delivery
- October & November
- Start of Project
- Collect Computer Parts: Motherboards, CPU, Disk,
- Decide on OS (Ubuntu), Kiosk (Freedom Toaster), Software
- Sketch Initial Design on Paper & Physical Dimensions of The Kiosk
- Decide on Physical Location of Kiosk (W-L Cyber Cafe)
- December
- Work on The Protocol
- Test Touchscreen
- January
- Test Protocol
- Decide on Contents
- February
- Aesthetic Design
- Develop Part List
- Final Design - CAD
- Order Parts
- March
- Assembly
- April
- Delivery The Kiosk To Physical Location